资源管理 中等 People 人域 题号 PMP202611-082

题目

在一个技术项目进行到中期时,一名关键团队成员被要求转去另一个项目。团队认为这样做风险很大,并对此感到担忧。以下哪项行动最有助于解决问题?
During the middle of a technical project, a key team member is requested to shift to another project. The team considers this risky and is concerned. Which action will best help resolve the issue?

选项

  1. A.Discuss the conflict with the project sponsor and formulate a response
  2. B.Use coaching tools and techniques to motivate the project team
  3. C.Replace the key team member with a new resource who has the same skills
  4. D.Acknowledge the team's concern and analyze the impact to the project
正确答案:D

解析

解析:项目经理必须妥善处理重大人员变动,同时保持团队的投入度和产出。先承认团队担忧并分析真实影响,既能建立信任,也为后续决策提供依据;直接换人或上报都为时过早。 Rationale:The project manager must handle significant personnel changes while keeping the team engaged and productive. Acknowledging the concern and analyzing the actual impact builds trust and produces the facts needed for later decisions; jumping to replacement or escalation is premature.