题目
项目进行中,一位相关方要求增加一个原范围之外的小功能,开发人员未经批准就加上了。这属于什么?
During a project, a stakeholder requests a small feature that was not in the original scope. The developer adds it without approval. What does this represent?
选项
- A.Gold Plating
- B.Scope Creep
- C.Progressive Elaboration
- D.Integrated Change Control
解析
解析:范围蔓延是指范围在未相应调整进度、预算或资源的情况下失控扩张。
Rationale:Scope creep refers to the uncontrolled expansion of scope without adjustments to the schedule, budget, or resources.