你项目的指导委员会必须审批变更,但没有人设定审批权限。你把每个小变更都提交委员会,现在决策需要三周。你应该怎么做?
Your project’s steering committee must approve changes, but nobody has set approval limits. You send every small change to the committee, and decisions now take three weeks. What should you do?
选项
- A.Stop sending changes and approve all of them yourself.
- B.Work with the sponsor and steering committee to set approval thresholds and escalation paths.
- C.Collect changes and submit them once a quarter.
- D.Ask the team to stop raising change requests.
解析
解析:考纲要求建立治理机制,明确权限与上报路径。清晰的阈值让你可批准小变更、只把重大变更提交委员会;若全部自行批准,则越权行事。
Rationale:The ECO asks you to set up governance, with clear limits and escalation paths. Clear limits let you approve small changes and send only large ones to the committee. If you approve every change yourself, you act beyond your role.