质量管理计划与目的 · PMP 练习题解析

质量管理 中等 Process 过程域 题号 PMP202611-021

题目

三周内,组装产品的缺陷率从 2% 上升到 6%。团队建议在发货前对每台产品逐一检验。你首先应该做什么?
Over three weeks, the defect rate on assembled units rises from 2% to 6%. The team suggests inspecting every unit before shipping. What should you do first?

选项

  1. A.Add a final inspection for every unit.
  2. B.Find the root cause of the increase before choosing a fix.
  3. C.Replace the parts supplier.
  4. D.Accept the higher rate because it is still below 10%.
正确答案:B

解析

解析:预防的成本低于检验。根因分析能揭示变化所在,使纠正措施对准真正的问题。增加检验只能发现缺陷而不能预防缺陷,更换供应商则是猜测。 Rationale:Prevention costs less than inspection. Root cause analysis tells you what changed, so the fix targets the real problem. More inspections catch defects but don’t prevent them, and changing the supplier is a guess.