题目
发起人表示每周状态报告长达 20 页,他找不到自己需要的信息,并已开始直接给团队成员打电话了解进展。你应该怎么做?
Your sponsor says the weekly status report is 20 pages long and he cannot find what he needs. He has started calling team members directly for updates. What should you do?
选项
- A.Keep the current format because the PMO template requires it.
- B.Ask the sponsor what information he needs and how often, then tailor a short report or dashboard.
- C.Send the report every two weeks instead of weekly.
- D.Ask a team member to write the report from now on.
解析
解析:考纲要求理解报告需求,并按发起人的期望设计报告。模板只是起点,可与 PMO 协商定制版本;仅调整频率并不能解决内容问题。
Rationale:The ECO asks you to understand reporting needs and create reports aligned with sponsor expectations. A template is a starting point, and you can agree on a tailored version with the PMO. Changing frequency alone does not fix the content.