第二次发布后,客户满意度评分下降。反馈称功能运行正常,但新报表不易阅读。你应该怎么做?
After the second release, the customer satisfaction score drops. Feedback says the features work, but the new reports are hard to read. What should you do?
选项
- A.Explain that the reports meet the signed-off requirements.
- B.Review the feedback with the customer and product owner, then prioritize report improvements.
- C.Stop running satisfaction surveys until the project ends.
- D.Submit a change request to lower the acceptance criteria.
解析
解析:考纲要求持续监测客户满意度并及时响应。若客户无法获得价值,仅仅“符合需求文字”是不够的。为旧设计辩护或隐瞒反馈都会损害信任。
Rationale:The ECO asks you to monitor customer satisfaction and respond as needed. Meeting the letter of the requirements is not enough if the customer cannot get value. Defending the old design or hiding the feedback damages trust.