题目
你带领一支新组建的敏捷团队。每天早上,团队成员都等着你指派工作。只要你参加其他会议,进度就会变慢。你应该怎么做?
You lead a newly formed agile team. Every morning, team members wait for you to tell them what to work on. Progress slows whenever you are in other meetings. What should you do?
选项
- A.Keep assigning tasks each morning so nobody is confused.
- B.Coach the team to pull work from the board and make daily decisions together.
- C.Ask the functional manager to replace the passive team members.
- D.Build a detailed task schedule for each person.
解析
解析:敏捷团队在被授权、自组织时表现最好。作为服务型领导,你应辅导团队走向自组织。事事指派会让你成为瓶颈,换人则忽略了真正的原因。
Rationale:Agile teams work best when they are empowered and self-organizing. As a servant leader, you coach them toward that. Assigning every task keeps you as the bottleneck, and replacing people ignores the real cause.