管理相关方参与 · PMP 练习题解析

相关方管理 困难 People 人域 题号 PMP202611-002

题目

一位新的区域总监在敏捷项目进行中途加入。她影响力很大,她的团队将使用该产品,但她尚未参加过任何迭代评审会。你应该采取哪两项行动?(选择两项)
A new regional director joins midway through an agile project. She has high influence, her team will use the product, and she has not attended any iteration reviews. Which two actions should you take? (Choose two.)

选项

  1. A.Meet her to learn her expectations and concerns.
  2. B.Update the stakeholder register and your plan to engage her.
  3. C.Send her the full project management plan and wait for questions.
  4. D.Pause all backlog changes until she approves them.
  5. E.Leave her off communications to avoid scope creep.
正确答案:A,B

解析

解析:新加入且影响力大的相关方需要尽早参与。首先与她沟通,然后更新让她持续参与的计划,这正是考纲对关键相关方的要求。冻结待办列表或把她排除在沟通之外都会带来风险。 Rationale:New, influential stakeholders need early engagement. First, you talk to her. Then you update how you will keep her involved. That is what the ECO asks you to do with key stakeholders. Freezing the backlog and excluding her both create risk.

同考点练习题