完工预测:EAC/ETC/TCPI/VAC · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-004

题目

某项目的完工预算(BAC)为 200,000 美元,挣值(EV)为 80,000 美元,实际成本(AC)为 100,000 美元。若当前成本绩效持续下去,完工估算(EAC)是多少?
A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $80,000 and the actual cost (AC) is $100,000. If current cost performance continues, what is the estimate at completion (EAC)?

选项

  1. A.$200,000
  2. B.$220,000
  3. C.$250,000
  4. D.$280,000
正确答案:C

解析

解析:成本绩效指数 CPI = EV / AC = 80,000 / 100,000 = 0.8;EAC = BAC / CPI = 200,000 / 0.8 = 250,000 美元。项目还需约 150,000 美元才能完成。 Rationale:CPI = EV / AC = 80,000 / 100,000 = 0.8. EAC = BAC / CPI = 200,000 / 0.8 = $250,000. The project will need about $150,000 more to finish.