挣值分析:偏差判读 · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-657

题目

某项目 CPI 为 0.85,SPI 为 1.15,说明什么?
A project has a CPI of 0.85 and an SPI of 1.15. What does this indicate?

选项

  1. A.The project is under budget and behind schedule
  2. B.The project is over budget and ahead of schedule
  3. C.The project is under budget and ahead of schedule
  4. D.The project is over budget and behind schedule
正确答案:B

解析

解析:CPI 小于 1 表示每花 1 元得到不足 1 元的价值(超支);SPI 大于 1 表示进展快于计划(超前)。 Rationale:CPI below 1 means each dollar buys less than a dollar of value (over budget); SPI above 1 means work is progressing faster than planned (ahead of schedule).

同考点练习题