题目
某项目 CPI 为 0.85,SPI 为 1.15,说明什么?
A project has a CPI of 0.85 and an SPI of 1.15. What does this indicate?
选项
- A.The project is under budget and behind schedule
- B.The project is over budget and ahead of schedule
- C.The project is under budget and ahead of schedule
- D.The project is over budget and behind schedule
解析
解析:CPI 小于 1 表示每花 1 元得到不足 1 元的价值(超支);SPI 大于 1 表示进展快于计划(超前)。
Rationale:CPI below 1 means each dollar buys less than a dollar of value (over budget); SPI above 1 means work is progressing faster than planned (ahead of schedule).