项目章程与立项 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-142

题目

你在某国管理一个关键基础设施项目,法规要求施工前必须取得五个政府部门的书面批准。发起人施压要求立即开始地基施工以赶上原定工期,并称许可“只是手续”,可以边施工边办理。最合适的做法是?
You manage a critical infrastructure project in a country where regulatory compliance requires documented approval from five government agencies before construction can begin. Your sponsor pressures you to start foundation work immediately to meet the original timeline, arguing that permits are 'just formalities' that can be obtained in parallel with construction. What is the most appropriate action?

选项

  1. A.Begin foundation work immediately as requested by the sponsor while continuing permit applications in parallel to maintain schedule
  2. B.Conduct a thorough risk assessment of the business environment and regulatory landscape, document the compliance requirements and their dependencies, and present a realistic schedule and risk analysis to the sponsor showing the impact of non-compliance
  3. C.Request that the sponsor personally contact the government agencies to expedite the permits without any formal documentation
  4. D.Halt all project activities until every regulatory approval is secured, even if it requires extending the timeline indefinitely
正确答案:B

解析

解析:PMI 道德准则要求严格遵守法律法规,即使发起人施压也不能绕过许可。项目经理应评估并记录监管依赖关系,用事实性的进度与风险分析说明不合规在法律、财务与工期上的后果,同时继续推进非施工类工作。 Rationale:The PMI Code of Ethics requires strict adherence to laws and regulations; permits cannot be bypassed even under sponsor pressure. The PM should assess and document the regulatory dependencies and present a factual schedule and risk analysis showing the legal, financial, and schedule consequences of non-compliance, while keeping non-construction work moving.