题目
你的项目正在为一家地区医院交付新的病历系统。上线前八周,内部合规官指出系统的数据保留规则与最新修订的州医疗法规不一致;而该保留逻辑是按六个月前法务批准的原始规格构建的。项目经理首先应该做什么?
Your project is delivering a new patient records system for a regional hospital. Eight weeks before go-live, an internal compliance officer flags that the system's data retention rules do not align with newly updated state healthcare regulations. The retention logic was built to the original specification, which legal approved six months ago. What should the project manager do FIRST?
选项
- A.Submit a change request to update the retention logic to match the new regulations.
- B.Escalate to the sponsor and recommend pausing the project until legal provides updated guidance.
- C.Assess the gap between current system behaviour and the new requirements, then bring options to the sponsor with cost and schedule impact.
- D.Continue with go-live and address the gap in a post-launch release, since the original specification was approved by legal.
解析
解析:项目中途出现的合规变化需要项目经理主导影响评估:先量化差距,再形成带成本与进度后果的选项,最后由发起人决策。不了解差距就无法写出有意义的变更请求,没有选项就无法建议暂停,而合规缺口也不能拖延——系统一上线法律风险就已产生。
Rationale:Compliance changes that land mid-project require a PM-led impact assessment: measure the gap, build options with cost and schedule consequences, then let the sponsor decide. You cannot write a meaningful change request before knowing the gap, cannot recommend a pause without options, and cannot defer a compliance gap because legal exposure starts at go-live.
同考点练习题
-
PMP202611-058 · 答案 B
-
PMP202611-095 · 答案 C
-
PMP202611-142 · 答案 B
-
PMP202611-269 · 答案 B
-
PMP202611-330 · 答案 D
-
PMP202611-441 · 答案 D
-
PMP202611-565 · 答案 A
-
PMP202611-656 · 答案 B