项目章程与立项 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-269

题目

某项目按时、在预算内完成交付,但效益实现计划显示预期的业务成果将无法达成。这应如何定性?
A project was delivered on time and within budget, but the benefits realisation plan shows that projected business outcomes will not be achieved. How should this be classified?

选项

  1. A.A successful project: it was delivered on time and within budget.
  2. B.A failed project: delivering outputs without achieving outcomes does not constitute project success.
  3. C.A partially successful project, the delivery constraints were met even if outcomes were not.
  4. D.An operations issue: benefits realisation is outside the project manager's responsibility.
正确答案:B

解析

解析:B 正确。PMBOK 第 8 版与 2023 版 ECO 明确指出,项目成功必须以业务成果衡量,而不仅是交付约束。按时按预算交付却未产生预期业务效益的项目,并未真正成功。Business Environment 领域正是考查从“产出导向”转向“成果导向”的成功观。A、C 仍是过时的铁三角思维;D 错误地把成果责任排除在项目经理之外。 Rationale:B is correct. PMBOK 8 and the ECO 2023 explicitly recognise that project success must be measured against business outcomes, not just delivery constraints. A project that delivers on time and on budget but fails to produce the intended business benefit has not succeeded in the full sense. The Business Environment domain specifically tests this shift from output-focused to outcome-focused project success. Options A and C apply outdated iron-triangle thinking. D incorrectly excludes the PM from outcome responsibility.

同考点练习题