题目
项目经理正在编制项目章程。下列哪项赋予项目经理调配项目资源的权限?
A project manager is preparing a project charter. Which of the following gives the project manager the authority to apply project resources?
选项
- A.The scope baseline.
- B.The project management plan.
- C.The stakeholder register.
- D.The project charter. It formally authorises the project and gives the project manager authority to apply organisational resources to project activities.
解析
解析:D 正确。项目章程正式授权项目存在,并赋予项目经理调配组织资源的权限。这是 PMBOK 考查频率最高的概念之一。章程由项目之外的发起人签发——正是这份外部授权构成了项目经理的职权来源。项目管理计划(B)指导执行但不授予权限;范围基准(A)与相关方登记册(C)都是规划输出。
Rationale:D is correct. The project charter formally authorises the existence of the project and grants the project manager the authority to apply organisational resources. This is one of the most frequently tested PMBOK concepts. The charter is issued by the sponsor, who sits outside the project: that external authority is what gives the PM their mandate. The project management plan (B) guides execution but doesn't grant authority. Scope baseline (A) and stakeholder register (C) are planning outputs.
同考点练习题
-
PMP202611-058 · 答案 B
-
PMP202611-095 · 答案 C
-
PMP202611-142 · 答案 B
-
PMP202611-204 · 答案 C
-
PMP202611-269 · 答案 B
-
PMP202611-330 · 答案 D
-
PMP202611-565 · 答案 A
-
PMP202611-656 · 答案 B