题目

某全球项目在多地使用多家分包商。为加快交付,客户经常绕过项目经理直接向分包团队下指令,导致优先级冲突、重复工作与集成问题,分包商也搞不清最终决策权在谁手上。项目经理应当怎么做?
A global project uses multiple subcontractors across regions. To accelerate delivery, the customer frequently bypasses the PM and sends direct instructions to subcontractor teams, causing conflicting priorities, duplicate work and integration issues. Subcontractors are confused about who has final decision authority. What should the PM do?

选项

  1. A.Define communication rules and remind the client to route requests through the project manager.
  2. B.Establish a governance framework that defines decision rights, roles, escalation paths, and communication boundaries.
  3. C.Schedule daily alignment calls between the customer and subcontractor teams to improve direct clarification.
  4. D.Escalate the issue to procurement to modify subcontractor agreements with stricter communication clauses.
正确答案:B

解析

解析:核心问题不是沟通不足,而是缺乏结构化的权责与协调规则。建立治理框架才能既恢复清晰边界,又保留必要的协作。 Rationale:The core issue is not lack of communication but lack of structured authority and coordination rules; a governance framework restores clarity while permitting needed collaboration.