在一个预测型软件项目中,客户直接给一名开发人员发邮件,要求增加一份报表。开发人员表示只需两个小时。项目经理应该怎么做?
On a predictive software project, the customer emails a developer and asks for an extra report. The developer says it will take only two hours. What should the project manager do?
选项
- A.Let the developer build it because the effort is small.
- B.Assess the impact of the request and process it through change control.
- C.Reject the request because the scope is baselined.
- D.Add the report now and tell the customer later.
解析
解析:再小的变更也需要受控管理,跳过流程会导致范围蔓延;直接拒绝则忽视了客户的合理需求。
Rationale:Small changes still need control. Skipping the process leads to scope creep. Rejecting it outright ignores a valid customer need.