整体变更控制 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-006

题目

在一个预测型软件项目中,客户直接给一名开发人员发邮件,要求增加一份报表。开发人员表示只需两个小时。项目经理应该怎么做?
On a predictive software project, the customer emails a developer and asks for an extra report. The developer says it will take only two hours. What should the project manager do?

选项

  1. A.Let the developer build it because the effort is small.
  2. B.Assess the impact of the request and process it through change control.
  3. C.Reject the request because the scope is baselined.
  4. D.Add the report now and tell the customer later.
正确答案:B

解析

解析:再小的变更也需要受控管理,跳过流程会导致范围蔓延;直接拒绝则忽视了客户的合理需求。 Rationale:Small changes still need control. Skipping the process leads to scope creep. Rejecting it outright ignores a valid customer need.

同考点练习题