整体变更控制 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-125

题目

一个医疗软件项目进行到中途时,新出台的数据隐私法规对患者信息存储方式提出要求,且该法规在项目计划完工日期之前生效。项目经理应该怎么做?
Midway through a healthcare software project, a new data privacy regulation is enacted that affects how patient information must be stored. The regulation takes effect before the project's planned completion date. What should the project manager do?

选项

  1. A.Complete the project as planned and address compliance in a future release
  2. B.Submit a change request to incorporate the new regulatory requirements into the project scope
  3. C.Cancel the project since the original scope is no longer viable under the new regulation
  4. D.Ask the legal team to request a compliance extension from the regulatory body
正确答案:B

解析

解析:当新法规影响可交付成果时,项目经理应通过整体变更控制提交变更请求。法规在完工前生效,合规要求不能拖延;取消项目为时过早,而向监管机构申请延期通常超出项目权限。 Rationale:When new regulations affect deliverables, the project manager initiates a change request through integrated change control. Compliance requirements cannot be deferred when they take effect before completion; canceling is premature, and requesting regulatory extensions is typically outside the project's authority.