配置管理关注的是什么?
What is configuration management focused on?
选项
- A.Identification and correction of problems arising in functional areas of project implementation
- B.The specification of both the deliverables and the processes, while change control focuses on identifying, documenting, and approving or rejecting changes to project documents, deliverables, or baselines
- C.Testing new systems
- D.Identifying, documenting, and controlling changes to project and product baselines, while change control focuses on deliverable and process specifications
解析
解析:配置控制关注可交付成果与过程的规范说明,确保产品属性一致;变更控制关注识别、记录并批准或否决对文件、可交付成果或基准的变更。
Rationale:Configuration control focuses on the specifications of deliverables and processes, ensuring consistency of product attributes. Change control focuses on identifying, documenting, and approving or rejecting changes to documents, deliverables, or baselines.