整体变更控制 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-066

题目

某项目为符合一项新的环保法规而启动。六个月后该法规更新,现有范围已无法保证合规。项目经理首先应该做什么?
A project was initiated to comply with a new environmental regulation. Six months later, the regulation is updated and the current scope no longer ensures compliance. What should the project manager do first?

选项

  1. A.Pause all project work until legal guidance is provided
  2. B.Perform a gap analysis between the current scope and the new legal requirements
  3. C.Submit a change request to update the project scope
  4. D.Continue executing the current plan to avoid delays
正确答案:B

解析

解析:在提交变更请求或停工之前,项目经理必须先分析新法规对现有范围的影响。 Rationale:Before submitting a change request or halting work, the project manager must first analyze how the new regulation impacts the current scope.

同考点练习题