题目
某项目为符合一项新的环保法规而启动。六个月后该法规更新,现有范围已无法保证合规。项目经理首先应该做什么?
A project was initiated to comply with a new environmental regulation. Six months later, the regulation is updated and the current scope no longer ensures compliance. What should the project manager do first?
选项
- A.Pause all project work until legal guidance is provided
- B.Perform a gap analysis between the current scope and the new legal requirements
- C.Submit a change request to update the project scope
- D.Continue executing the current plan to avoid delays
解析
解析:在提交变更请求或停工之前,项目经理必须先分析新法规对现有范围的影响。
Rationale:Before submitting a change request or halting work, the project manager must first analyze how the new regulation impacts the current scope.