题目
并非所有成员都按规定办理项目所用资源的领用登记。项目经理最佳的做法是:
Not all team members are properly checking out resources used in the project. What is the best course of action for the project manager?
选项
- A.Capture the issue and its priority in the issue log
- B.Escalate the issue to the functional managers
- C.Discuss the checkout rationale with the team
- D.Update the plans to reflect the actual situation
解析
解析:这类行为规范问题,先讲清“为什么”让团队理解并自行纠正,比直接上报更有效。
Rationale:Behavioral compliance problems are best addressed by explaining the rationale to the team so they understand and self-correct, rather than by escalation.