题目
一位高层相关方通过邮件提出重大范围变更。项目经理应该怎么做?
A senior stakeholder requests a major scope change via email. What should the project manager do?
选项
- A.Implement the change immediately
- B.Reject the change because it was not planned
- C.Review the request through the formal change control process
- D.Escalate the request to the steering committee
解析
解析:所有变更请求都必须走既定的变更控制流程,以评估其对范围、成本、进度和质量的影响。
Rationale:All change requests must follow the established change control process to evaluate impacts on scope, cost, schedule, and quality.
同考点练习题
-
PMP202611-006 · 答案 B
-
PMP202611-056 · 答案 C
-
PMP202611-066 · 答案 B
-
PMP202611-093 · 答案 D
-
PMP202611-116 · 答案 B
-
PMP202611-125 · 答案 B
-
PMP202611-191 · 答案 B
-
PMP202611-206 · 答案 C