整体变更控制 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-031

题目

一位高层相关方通过邮件提出重大范围变更。项目经理应该怎么做?
A senior stakeholder requests a major scope change via email. What should the project manager do?

选项

  1. A.Implement the change immediately
  2. B.Reject the change because it was not planned
  3. C.Review the request through the formal change control process
  4. D.Escalate the request to the steering committee
正确答案:C

解析

解析:所有变更请求都必须走既定的变更控制流程,以评估其对范围、成本、进度和质量的影响。 Rationale:All change requests must follow the established change control process to evaluate impacts on scope, cost, schedule, and quality.