题目
客户应用项目进行到一半时,一项新的数据保护法规开始生效。你首先应该做什么?
A new data-protection regulation comes into force midway through your customer app project. What should you do first?
选项
- A.Continue as planned.
- B.Work with legal and compliance experts to assess the impact, then update requirements and plans through change control.
- C.Remove all customer data from the app.
- D.Delay the launch for a year.
解析
解析:法规合规是强制要求。与专家评估影响可明确必须改动什么,随后以受控方式更新计划。
Rationale:Regulatory compliance is mandatory. Assessing the impact with experts shows exactly what must change, then the plan is updated in a controlled way.