整体变更控制 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-646

题目

与客户进行产品评审时,尽管交付物此前已通过验证,客户仍发现缺陷并拒收其中一项。你应当怎么做?
During a product review with the client, although deliverables were previously verified, the client detects a defect and rejects one deliverable. What should you do?

选项

  1. A.Submit a change request to fix the deliverable
  2. B.Refund the customer for the value of the deliverable
  3. C.Ask the project team to repair the defect
  4. D.Begin the claims administration process
正确答案:A

解析

解析:范围确认中被拒收的交付物会生成返工变更请求,再走整体变更控制流程。 Rationale:Rejected deliverables during Validate Scope generate a change request for rework, which then flows through integrated change control.