成本估算与估算责任 · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-645

题目

某活动需要在大范围搜索失败原型爆炸后的碎片。规划阶段团队就所需资源的类型与数量争论不休。项目经理首先应当做什么?
One activity requires searching a large area for debris from an explosion of a failed prototype. In planning, the team debates the type and quantity of resources needed. What should the PM do first?

选项

  1. A.Select any resource and quantity to complete the task by the due date
  2. B.Request the team to vote and make a decision based on majority
  3. C.Research various levels of resource capability and skills, types, and sizes
  4. D.Utilize a PMIS to manage resource pools and allocate resources
正确答案:C

解析

解析:估算活动资源要靠数据分析评估各选项与取值范围;先把能力、技能、类型与规模调查清楚,估算才有依据。 Rationale:Estimate Activity Resources relies on data analysis to evaluate options and ranges; researching capability, skills, types and sizes informs a defensible estimate.

同考点练习题