某活动需要在大范围搜索失败原型爆炸后的碎片。规划阶段团队就所需资源的类型与数量争论不休。项目经理首先应当做什么?
One activity requires searching a large area for debris from an explosion of a failed prototype. In planning, the team debates the type and quantity of resources needed. What should the PM do first?
选项
- A.Select any resource and quantity to complete the task by the due date
- B.Request the team to vote and make a decision based on majority
- C.Research various levels of resource capability and skills, types, and sizes
- D.Utilize a PMIS to manage resource pools and allocate resources
解析
解析:估算活动资源要靠数据分析评估各选项与取值范围;先把能力、技能、类型与规模调查清楚,估算才有依据。
Rationale:Estimate Activity Resources relies on data analysis to evaluate options and ranges; researching capability, skills, types and sizes informs a defensible estimate.