管理团队:绩效与冲突 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-143

题目

在为新产品开发项目规划范围时,发起人与关键技术相关方对某项功能是否属于范围存在分歧:发起人认为它对业务价值不可或缺,技术负责人则认为在工期约束下会带来不可接受的技术风险。你主持工作会议来解决分歧。决策过程中最合适的第一步是?
While planning scope for a new product development project, your sponsor and key technical stakeholders disagree on whether a specific feature is within scope. The sponsor sees it as essential to business value, while the technical lead argues it introduces unacceptable technical risk given schedule constraints. You facilitate a working session to resolve the disagreement. What is the most appropriate first step in the decision-making process?

选项

  1. A.Conduct a risk assessment on the disputed feature, document the technical risks and mitigation options, and present the analysis so the sponsor and technical lead can make an informed decision based on data
  2. B.Ask the sponsor and technical lead to reach a compromise by reducing the feature's scope to make it technically feasible within the schedule
  3. C.Escalate the disagreement to the project steering committee immediately so governance authority can make the final decision
  4. D.Defer the feature to a future release phase to avoid delaying the current project and eliminate the conflict entirely
正确答案:A

解析

解析:合作(问题解决)把冲突视为可通过客观审视方案与数据来解决的问题。分歧本质是业务价值与技术风险的权衡,项目经理应先推动风险评估,让讨论建立在事实而非主观判断之上。 Rationale:Collaborating (problem-solving) treats conflict as a problem to be resolved through objective examination of alternatives and data. Because the disagreement is a trade-off between business value and technical risk, the PM first facilitates a risk assessment so the discussion becomes factual rather than subjective.