题目
在你负责的预测型设计项目中,两位资深工程师对某个结构方案意见不合,争论已演变为针对个人,其他团队成员开始回避会议。你首先应该做什么?
Two senior engineers on your predictive design project disagree about a structural approach. The argument has turned personal, and other team members now avoid meetings. What should you do first?
选项
- A.Ask their line manager to step in and settle it.
- B.Meet both engineers privately to understand the source of the disagreement.
- C.Choose the approach you prefer so the work can continue.
- D.Ask the whole team to vote on the approach at the next meeting.
解析
解析:考纲要求项目经理先识别冲突来源并分析情境,再选择解决方式。立即上报为时过早;强行拍板会损害信任;投票表决则回避了根本原因。
Rationale:The ECO asks you to identify conflict sources and analyze the context before choosing a resolution. Escalation is premature, forcing a decision harms trust, and a vote avoids the root cause.