进度计划制定与承诺 · PMP 练习题解析

进度管理 困难 Process 过程域 题号 PMP202611-644

题目

你在一个受多级政府严格监管的地点建桥,正在编制一份规定进度“制定、监控与控制”准则与活动的计划。完成该过程应收集什么?
You manage a bridge project in a location highly regulated by multiple levels of government, and are developing a plan establishing criteria and activities for developing, monitoring and controlling the schedule. What should you gather to complete this process?

选项

  1. A.The charter, project management plan, estimation databases, and PMO templates
  2. B.Government standards, the assumption log, schedule management plan, and milestone list
  3. C.The resource breakdown structure, lessons learned register, and scheduling methodology
  4. D.The project scope statement, risk register, and project team assignments
正确答案:A

解析

解析:规划进度管理有四项输入:项目章程、项目管理计划、事业环境因素与组织过程资产——本题后两项分别由估算数据库与 PMO 模板体现。 Rationale:Plan Schedule Management takes four inputs: charter, project management plan, enterprise environmental factors and organizational process assets — the latter two represented here by estimation databases and PMO templates.

同考点练习题