题目
你在一个受多级政府严格监管的地点建桥,正在编制一份规定进度“制定、监控与控制”准则与活动的计划。完成该过程应收集什么?
You manage a bridge project in a location highly regulated by multiple levels of government, and are developing a plan establishing criteria and activities for developing, monitoring and controlling the schedule. What should you gather to complete this process?
选项
- A.The charter, project management plan, estimation databases, and PMO templates
- B.Government standards, the assumption log, schedule management plan, and milestone list
- C.The resource breakdown structure, lessons learned register, and scheduling methodology
- D.The project scope statement, risk register, and project team assignments
解析
解析:规划进度管理有四项输入:项目章程、项目管理计划、事业环境因素与组织过程资产——本题后两项分别由估算数据库与 PMO 模板体现。
Rationale:Plan Schedule Management takes four inputs: charter, project management plan, enterprise environmental factors and organizational process assets — the latter two represented here by estimation databases and PMO templates.