题目
敏捷团队的两名资深开发人员对软件架构存在根本分歧:一人主张微服务,另一人坚持单体架构,冲突已拖慢冲刺进度。项目经理应采用哪种冲突解决方式?
Two senior developers on an agile team have a fundamental disagreement about the software architecture. One advocates microservices while the other insists on a monolithic approach. The conflict is delaying sprint progress. Which conflict resolution technique should the project manager use?
选项
- A.Forcing: decide in favor of the developer with more seniority
- B.Compromising: implement a hybrid architecture that partially satisfies both
- C.Collaborating: facilitate a meeting where both present their approaches, evaluate trade-offs against project requirements, and reach a solution addressing the core concerns of both parties
- D.Withdrawing: let the team figure it out alone since the PM should not make technical decisions
解析
解析:对于重大技术分歧,合作(问题解决)是首选方式,因为它通过解决双方深层关切形成最持久的方案。强制会损害关系,妥协可能产生次优架构,回避则放弃了主持协调的责任。
Rationale:Collaborating (problem-solving) is preferred for significant technical disagreements because it produces the most durable solution by addressing underlying concerns. Forcing damages relationships, compromising may yield a suboptimal architecture, and withdrawing abdicates facilitation responsibility.