管理团队:绩效与冲突 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-026

题目

一名团队成员经常错过截止日期,影响项目进度。项目经理首先应该做什么?
A team member frequently misses deadlines, impacting the project schedule. What should the project manager do first?

选项

  1. A.Escalate the issue to the project sponsor
  2. B.Address the issue privately with the team member
  3. C.Reassign the member's tasks to more reliable team members
  4. D.Document the performance issue in the lessons learned register
正确答案:B

解析

解析:PMI 的思路强调先进行直接、私下的沟通,弄清根本原因,然后再考虑上报或采取纠正措施。 Rationale:The PMI mindset prioritizes direct, private communication to understand the root cause before escalating or applying corrective actions.

同考点练习题