题目
一名团队成员经常错过截止日期,影响项目进度。项目经理首先应该做什么?
A team member frequently misses deadlines, impacting the project schedule. What should the project manager do first?
选项
- A.Escalate the issue to the project sponsor
- B.Address the issue privately with the team member
- C.Reassign the member's tasks to more reliable team members
- D.Document the performance issue in the lessons learned register
解析
解析:PMI 的思路强调先进行直接、私下的沟通,弄清根本原因,然后再考虑上报或采取纠正措施。
Rationale:The PMI mindset prioritizes direct, private communication to understand the root cause before escalating or applying corrective actions.