管理团队:绩效与冲突 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-027

题目

你注意到两名团队成员在冲刺期间发生了激烈的技术争论。最佳应对方式是什么?
You notice two team members having a heated technical argument during a sprint. What is the best response?

选项

  1. A.Facilitate a discussion to help them reach a resolution
  2. B.Replace one of the team members to maintain harmony
  3. C.Immediately escalate the conflict to HR
  4. D.Ignore the conflict unless it affects project velocity
正确答案:A

解析

解析:在项目环境中冲突是正常的。项目经理应引导建设性对话,帮助团队找到有成效的解决方案。 Rationale:Conflict is natural in project environments. The project manager should facilitate constructive dialogue to help the team reach a productive solution.