题目
一名远程团队成员过去绩效优异,最近两次错过截止日期,在视频会议中也显得心不在焉。其他成员开始对其影响交付表示不满。项目经理首先应该做什么?
A remote team member who was previously a top performer has missed two deadlines and appears disengaged during video calls. Other team members have started expressing frustration about the impact on their deliverables. What should the project manager do first?
选项
- A.Issue a formal performance warning to document the decline
- B.Have a private, empathetic conversation with the team member to understand what may be affecting their performance
- C.Redistribute the team member's work to more reliable team members
- D.Discuss the performance issue during the next team retrospective to encourage accountability
解析
解析:情商要求项目经理在评判之前先以同理心接近绩效变化。私下沟通既维护个人尊严,也可能发现个人或职业层面的困难;警告、公开讨论或调岗都应在弄清根因之后再进行。
Rationale:Emotional intelligence requires approaching performance changes with empathy before judgment. A private conversation preserves dignity and may reveal personal or professional challenges; warnings, public discussion, or reassignment should follow only after the root cause is understood.