题目
团队汇报已完成“规划质量管理”:产出了质量管理计划,并更新了项目管理计划与项目文件。他们漏了什么?
The team reports they completed Plan Quality Management: they produced the quality management plan and updated the project management plan and project documents. What did they forget?
选项
- A.Determine quality metrics
- B.Define quality roles and responsibilities
- C.Revise the lessons learned register
- D.Update the requirements traceability matrix
解析
解析:质量量度是规划质量管理的一项独立输出,也是项目文件,用来描述要衡量什么属性以及如何验证合规。
Rationale:Quality metrics are a project document and a distinct output of Plan Quality Management; they describe attributes and how compliance will be verified.