题目
绩效审查发现重大偏差,若下次客户检查前不解决项目可能被取消。团队分析后认为只需对某配置项做小幅修正。首先应当做什么?
Reviewing performance you find a significant variance that could cancel the project at the next customer inspection. The team finds a minor correction to a configuration element is all that's needed. What should you do first?
选项
- A.Implement the corrective action
- B.Submit a change request
- C.Consult the project sponsor
- D.Delay the customer inspection
解析
解析:配置项处于配置控制之下,对它的任何变更都必须走正式控制,第一步就是提交变更请求。
Rationale:A configuration element is under configuration control; any change to it must be formally controlled and requires a change request first.