整体变更控制 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-607

题目

绩效审查发现重大偏差,若下次客户检查前不解决项目可能被取消。团队分析后认为只需对某配置项做小幅修正。首先应当做什么?
Reviewing performance you find a significant variance that could cancel the project at the next customer inspection. The team finds a minor correction to a configuration element is all that's needed. What should you do first?

选项

  1. A.Implement the corrective action
  2. B.Submit a change request
  3. C.Consult the project sponsor
  4. D.Delay the customer inspection
正确答案:B

解析

解析:配置项处于配置控制之下,对它的任何变更都必须走正式控制,第一步就是提交变更请求。 Rationale:A configuration element is under configuration control; any change to it must be formally controlled and requires a change request first.

同考点练习题