监控项目工作与绩效 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-608

题目

某工厂流程改进项目的项目经理正在执行“监控项目工作”过程。下列哪项活动可能在该过程中进行?
A PM leading a process improvement project for a factory is performing the Monitor and Control Project Work process. Which activity might be carried out during this process?

选项

  1. A.Comparing actual project performance against the project management plan
  2. B.Implementing approved change requests to achieve the project's objectives
  3. C.Analyzing change requests and either approving or rejecting them
  4. D.Gaining formal acceptance of the deliverables by the customer or sponsor
正确答案:A

解析

解析:监控项目工作负责跟踪、评审并报告对计划的整体进展;实施变更属于指导与管理项目工作,批准变更属于整体变更控制。 Rationale:Monitor and Control Project Work tracks, reviews and reports overall progress against the plan; implementing changes belongs to Direct and Manage Project Work, and approvals to integrated change control.