题目
某工厂流程改进项目的项目经理正在执行“监控项目工作”过程。下列哪项活动可能在该过程中进行?
A PM leading a process improvement project for a factory is performing the Monitor and Control Project Work process. Which activity might be carried out during this process?
选项
- A.Comparing actual project performance against the project management plan
- B.Implementing approved change requests to achieve the project's objectives
- C.Analyzing change requests and either approving or rejecting them
- D.Gaining formal acceptance of the deliverables by the customer or sponsor
解析
解析:监控项目工作负责跟踪、评审并报告对计划的整体进展;实施变更属于指导与管理项目工作,批准变更属于整体变更控制。
Rationale:Monitor and Control Project Work tracks, reviews and reports overall progress against the plan; implementing changes belongs to Direct and Manage Project Work, and approvals to integrated change control.
同考点练习题
-
PMP202611-111 · 答案 A
-
PMP202611-395 · 答案 D
-
PMP202611-460 · 答案 A
-
PMP202611-545 · 答案 D
-
PMP202611-574 · 答案 B
-
PMP202611-614 · 答案 B