管理沟通与绩效报告 · PMP 练习题解析

沟通管理 中等 Process 过程域 题号 PMP202611-606

题目

你接手一个执行中的项目,发现团队大量时间都在应付相关方临时的信息索取,导致项目活动被挤占、进度落后。首先应当做什么?
Taking over a project in execution, you find team members spend much time responding to unexpected stakeholder information requests, so activities slip and the project is behind schedule. What should you do first?

选项

  1. A.Tell the team members to stop responding, since it is not their responsibility
  2. B.Push the team to respond to all requests faster so they can perform assigned activities on time
  3. C.Ask the team to forward all stakeholder inquiries to you
  4. D.Review the communications management plan to understand how stakeholder requests should be handled
正确答案:D

解析

解析:监督沟通要先知道约定的问询渠道;查阅沟通管理计划,才能判断相关方是否偏离了约定。 Rationale:Monitor Communications requires knowing the agreed channeling of inquiries; review the communications management plan to judge whether stakeholders are violating the agreement.