资源管理 困难 People 人域 题号 PMP202611-597

题目

公司想提升敏捷团队绩效,多数成员远程办公。管理层问敏捷教练哪种做法正面影响最大,且预算不成问题。最佳建议是:
A company wants to improve agile team performance; most members work remotely. Management asks an agile coach for the approach with the biggest positive impact, and funds are not an issue. What is the best advice?

选项

  1. A.Upgrade the team's computers with the latest technology to increase work productivity
  2. B.Colocate the team members to improve team collaboration and communication
  3. C.Purchase additional software tools to improve the team's remote communication
  4. D.Assign a cubicle to each team member to help them better maintain their focus
正确答案:B

解析

解析:绩效取决于协作效果而非个人产出。集中办公带来面对面与“渗透式”沟通,正呼应“个体与互动高于流程与工具”。 Rationale:Performance is about working together effectively, not individual output. Co-location enables face-to-face and osmotic communication, honoring 'individuals and interactions over processes and tools'.