待办列表与优先级 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-530

题目

待办事项梳理(细化)的目的是:
Backlog refinement (grooming) is done to:

选项

  1. A.Assign blame
  2. B.Fire underperformers
  3. C.Write the project charter
  4. D.Ensure backlog items are clear, estimated, and ready for upcoming sprints
正确答案:D

解析

解析:梳理让待办列表顶部保持“就绪”:清楚、有估算、被理解,供冲刺计划直接取用。 Rationale:Refinement keeps the top of the backlog 'ready' — clear, sized, and understood — for sprint planning.