待办列表与优先级 · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-336

题目

团队正在梳理用户故事,其中一个故事被估算为 40 个故事点,远大于平常。产品负责人与团队应该怎么做?
A team is refining user stories and a story is estimated at 40 story points: much larger than usual. What should the Product Owner and team do?

选项

  1. A.Reduce the estimate by applying team pressure during planning poker.
  2. B.Accept the estimate and plan two sprints to complete the story.
  3. C.Decompose the story into smaller, independently deliverable stories that each fit within a single sprint. This is a fundamental backlog refinement activity.
  4. D.Assign the story to the most experienced developer to complete quickly.
正确答案:C

解析

解析:C 正确。大到无法在单个冲刺内完成的故事(即“史诗”)必须拆成更小、可独立交付的子故事,这是待办梳理的核心实践而非可选项。过大的故事带来冲刺承诺风险,也阻碍增量交付。接受跨冲刺故事(B)破坏冲刺边界原则;指派给一个人(D)不解决规模问题;人为压低估算(A)不诚实且会导致冲刺失败。 Rationale:C is correct. A story that is too large to complete within a sprint (an "epic") must be decomposed into smaller, independently deliverable stories. This is a core backlog refinement practice, not an optional activity. Large stories create sprint commitment risk and prevent incremental delivery. Accepting multi-sprint stories (B) breaks the sprint boundary principle. Assigning to one person (D) doesn't address the size issue. Artificial estimate reduction (A) is dishonest and leads to failed sprints.

同考点练习题