题目
团队正在梳理用户故事,其中一个故事被估算为 40 个故事点,远大于平常。产品负责人与团队应该怎么做?
A team is refining user stories and a story is estimated at 40 story points: much larger than usual. What should the Product Owner and team do?
选项
- A.Reduce the estimate by applying team pressure during planning poker.
- B.Accept the estimate and plan two sprints to complete the story.
- C.Decompose the story into smaller, independently deliverable stories that each fit within a single sprint. This is a fundamental backlog refinement activity.
- D.Assign the story to the most experienced developer to complete quickly.
解析
解析:C 正确。大到无法在单个冲刺内完成的故事(即“史诗”)必须拆成更小、可独立交付的子故事,这是待办梳理的核心实践而非可选项。过大的故事带来冲刺承诺风险,也阻碍增量交付。接受跨冲刺故事(B)破坏冲刺边界原则;指派给一个人(D)不解决规模问题;人为压低估算(A)不诚实且会导致冲刺失败。
Rationale:C is correct. A story that is too large to complete within a sprint (an "epic") must be decomposed into smaller, independently deliverable stories. This is a core backlog refinement practice, not an optional activity. Large stories create sprint commitment risk and prevent incremental delivery. Accepting multi-sprint stories (B) breaks the sprint boundary principle. Assigning to one person (D) doesn't address the size issue. Artificial estimate reduction (A) is dishonest and leads to failed sprints.