执行初期,你以很高的效率获得了设备、材料和物资,希望将这一最佳实践共享给相关方以改善本项目后续绩效。最佳做法是:
Early in execution, you obtain equipment, materials and supplies very efficiently. You want this best practice available to project stakeholders to improve future performance of the current project. What is your best course of action?
选项
- A.Document the best practice in the resource management plan
- B.Begin project closure as the project objectives have been achieved
- C.Add the knowledge gained to the enterprise environmental factors
- D.Inform the procurement department's manager of the best practice
解析
解析:获取资源过程的输出包括项目管理计划(含资源管理计划)的更新,把经验写进去才能真正影响后续绩效。
Rationale:Updates to the project management plan including the resource management plan are an output of Acquire Resources; documenting the practice there improves future performance.