已识别风险之一是公司留不住计划数量的合格开发人员,会影响进度。你需要判断该风险的发生可能性与影响。应当做什么?
One identified risk is that the company will be unable to retain the planned number of qualified developers, affecting the schedule. You need to determine the likelihood of this risk and its impact. What should you do?
选项
- A.Meet with the developers and get their input
- B.Create a probability and impact matrix
- C.Perform a risk data quality assessment
- D.Conduct a risk probability and impact assessment
解析
解析:实施定性风险分析正是通过评估发生概率与影响来排定风险优先级,所用技术就是风险概率与影响评估。
Rationale:Perform Qualitative Risk Analysis prioritizes risks by assessing probability of occurrence and impact; the risk probability and impact assessment is the technique for this.