效益实现与价值管理 · PMP 练习题解析

成本管理 中等 Process 过程域 题号 PMP202611-573

题目

内部项目接近完成,项目经理要与发起人开最后一次会,讨论交付物上线后如何最大化价值。用哪份文件支撑这次沟通?
An internal project is almost complete. The PM wants a final meeting with the sponsor to discuss how to maximize the value of the deliverables after deployment. What does the PM use to back up the conversation?

选项

  1. A.The benefits management plan
  2. B.The project charter
  3. C.The business case
  4. D.The activity list
正确答案:A

解析

解析:效益管理计划定义了效益如何被创造、放大与维持,包括交付物移交后应如何维护。 Rationale:The benefits management plan defines how benefits are created, maximized and sustained, including how deliverables should be maintained after handover.