题目
某敏捷团队交付的产品将带来显著的运营变革。业务发起人说“变革管理不是我们的问题,把软件交付出来就行”。这会产生什么风险,项目经理应如何应对?
An agile team is delivering a product that will require significant operational change. The business sponsor says "change management is not our problem: just deliver the software." What risk does this create and how should the project manager respond?
选项
- A.Deliver the software and then raise adoption issues as a new project after deployment.
- B.The risk is that technically successful delivery will produce no business benefit if users don't adopt the product. Raise this as a risk to the sponsor and propose including change management activities in the project plan or programme.
- C.Proceed with delivery and document the sponsor's position to protect the project team.
- D.Agree: change management is outside the project's scope and should be handled by operations.
解析
解析:B 正确。没有采纳的技术不会产生业务价值。Business Environment 领域考查的正是“以成果而非产出衡量成功”。项目经理若被动接受发起人的说法,就等于默许可预见的失败。正确做法是正式揭示采纳风险并提出方案,即便发起人最终不采纳。附和(D)无视成果风险;只做记录(C)过于被动;拖到上线后(A)等于永远不主动处理采纳缺口。
Rationale:B is correct. Technology without adoption delivers no business value. The Business Environment domain tests understanding that project success is measured by outcomes, not outputs. A PM who passively accepts this sponsor position is complicit in a predictable failure. The correct response is to surface the adoption risk formally and propose a solution, even if the sponsor ultimately decides not to act on it. Agreeing (D) ignores the outcome risk. Documentation only (C) is passive. Deferring (A) ensures the adoption gap is never addressed proactively.