效益实现与价值管理 · PMP 练习题解析

成本管理 困难 Process 过程域 题号 PMP202611-210

题目

你的项目将交付产出,但效益取决于组织是否采纳新的工作方式。谁通常对实现这些效益负责?
Your project will deliver its output, but the benefits depend on the organisation adopting a new way of working. Who is typically accountable for realising those benefits?

选项

  1. A.The project manager alone.
  2. B.The project team that built the output.
  3. C.The sponsor or business owner, supported by the project.
  4. D.The PMO that tracks the schedule.
正确答案:C

解析

解析:效益在交付之后于业务侧实现,因此由发起人或业务负责人担责,项目负责使能采纳与度量。项目经理交付产出,但不拥有业务结果。 Rationale:Benefits accrue in the business after delivery, so the sponsor or business owner is accountable, with the project enabling adoption and measurement. The PM delivers the output but does not own the business outcome.