发起人索要刚关闭项目的绩效与结果概览:项目总体说明、质量与成本评估、范围目标及达成标准的完成情况。你应提供哪份文件?
Your sponsor asks for an overview of performance and outcome of a recently closed project: a description of the overall project, quality and cost evaluations, and completion of scope objectives and criteria. What document will you provide?

选项

  1. A.The cost and scope baseline report
  2. B.Final report
  3. C.Quality report
  4. D.Project charter
正确答案:B

解析

解析:最终报告汇总项目各领域的绩效,包括质量目标与评估标准、验证与交付日期、最终成果的确认信息,以及遇到的风险与问题及处理情况。 Rationale:The final report summarizes project performance across areas: quality objectives and criteria, verification and delivery dates, validation info, and risks or issues encountered.