题目
你的项目在六个月前交付了新的客户入驻门户。商业论证预计入驻时间缩短 50%、每年节省 240 万;实际运行六个月后,入驻时间仅下降 18%,年化节省约 70 万。发起人要求汇报效益实现情况。正确的回应是什么?
Your project delivered a new customer onboarding portal six months ago. The business case projected a 50% reduction in onboarding time and 2.4M in annual savings. Six months in, onboarding time has dropped 18% and savings are running at 700K annualised. The sponsor asks for a status update on benefits realisation. What is the correct response?
选项
- A.Report that benefits realisation is below projections and recommend a project review to identify why.
- B.Explain that benefits realisation is the sponsor's responsibility, not the PM's, once the project has been formally closed.
- C.Report the current numbers and document the variance, but note that benefits tracking continues per the benefits management plan.
- D.Update the business case retroactively to reflect the actual benefits achieved.
解析
解析:效益实现并不随项目关闭而终止,而是按效益管理计划持续进行。正确做法是汇报真实数据(透明)、记录偏差(可问责),并在既定窗口内继续跟踪。直接跳到评审跳过了汇报步骤;回溯改写商业论证则会抹掉组织学习所需的偏差信号。
Rationale:Benefits realisation does not end at project closure; it continues per the benefits management plan. The correct response reports actual numbers (transparency), documents the variance (accountability), and keeps tracking within the agreed window. Jumping to a review skips the reporting step, and rewriting the business case destroys the variance signal the organisation needs to learn.