发起人希望证明确认:CRM 项目上线后能减少客户投诉。你在规划阶段应做什么?
The sponsor wants proof that your CRM project will reduce customer complaints after go-live. What should you do during planning?
选项
- A.Promise the benefit in the charter.
- B.Define measurable benefits, a benefit owner and a timeline in a benefits management plan.
- C.Measure complaints only during the project.
- D.Leave benefits to the operations team.
解析
解析:效益往往在项目收尾后才显现,因此效益管理计划要明确衡量什么、由谁衡量、何时衡量,从而把项目产出与商业价值挂上钩。
Rationale:Benefits often materialise after the project closes, so a benefits management plan specifies what is measured, by whom and when. This links project output to business value.