题目
一位刚入职的高管发邮件,要求接收项目的全部沟通信息。项目经理下一步应当做什么?
A project manager receives an email from a new executive who has just joined the company, requesting to be included in all communications about the project. What should the PM do next?
选项
- A.Decline the request
- B.Submit a change request
- C.Consult with the sponsor
- D.Meet with the executive
解析
解析:在改动任何文件前,先弄清这位相关方要什么、与项目有什么利害关系——高管通常需要摘要而非每条信息。先面谈,再调整参与安排。
Rationale:Understand the stakeholder's needs and stake before updating documents — an executive likely needs a summary rather than every message. Meet first, then adjust engagement arrangements.