市场变化使项目商业论证中的预期效益已无法实现。项目经理应建议什么?
A market shift makes the expected benefits in the project’s business case no longer achievable. What should the project manager recommend?
选项
- A.Close the project immediately
- B.Update the benefits management plan and request a re-evaluation
- C.Reduce the technical scope to lower costs
- D.Delay sharing the findings until the project nears completion
解析
解析:预期效益发生变化时,应依据效益管理计划重新评估项目,确认其是否仍能交付价值。
Rationale:When expected benefits change, the project must be reassessed using the benefits management plan to confirm whether it still delivers value.