效益实现与价值管理 · PMP 练习题解析

成本管理 困难 Process 过程域 题号 PMP202611-068

题目

市场变化使项目商业论证中的预期效益已无法实现。项目经理应建议什么?
A market shift makes the expected benefits in the project’s business case no longer achievable. What should the project manager recommend?

选项

  1. A.Close the project immediately
  2. B.Update the benefits management plan and request a re-evaluation
  3. C.Reduce the technical scope to lower costs
  4. D.Delay sharing the findings until the project nears completion
正确答案:B

解析

解析:预期效益发生变化时,应依据效益管理计划重新评估项目,确认其是否仍能交付价值。 Rationale:When expected benefits change, the project must be reassessed using the benefits management plan to confirm whether it still delivers value.

同考点练习题