整体变更控制 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-571

题目

资源管理计划因仓储有限,规定木材采用小批量准时制(JIT)配送。执行中项目经理发现可从新供应商一次性大批量低价采购,即便加上额外仓储费也省下不少。最佳做法是:
The resource management plan specifies just-in-time lumber delivery in small shipments due to limited storage. During execution, the PM learns of an opportunity to buy lumber in one shipment at greatly reduced price from a new supplier; even with extra storage costs the savings would be significant. What is the best course of action?

选项

  1. A.Submit a change request through the Perform Integrated Change Control process
  2. B.Follow the resource management plan as originally specified
  3. C.Proceed with the acquisition of the lumber and storage facility to reduce project costs
  4. D.Add the supplier to the preapproved seller list
正确答案:A

解析

解析:改变配送与仓储方式等于修改资源管理计划,而它是项目管理计划的子计划,必须经批准的变更请求。 Rationale:Changing delivery and storage approach modifies the resource management plan, a subsidiary of the project management plan, so an approved change request is required.

同考点练习题