题目
资源管理计划因仓储有限,规定木材采用小批量准时制(JIT)配送。执行中项目经理发现可从新供应商一次性大批量低价采购,即便加上额外仓储费也省下不少。最佳做法是:
The resource management plan specifies just-in-time lumber delivery in small shipments due to limited storage. During execution, the PM learns of an opportunity to buy lumber in one shipment at greatly reduced price from a new supplier; even with extra storage costs the savings would be significant. What is the best course of action?
选项
- A.Submit a change request through the Perform Integrated Change Control process
- B.Follow the resource management plan as originally specified
- C.Proceed with the acquisition of the lumber and storage facility to reduce project costs
- D.Add the supplier to the preapproved seller list
解析
解析:改变配送与仓储方式等于修改资源管理计划,而它是项目管理计划的子计划,必须经批准的变更请求。
Rationale:Changing delivery and storage approach modifies the resource management plan, a subsidiary of the project management plan, so an approved change request is required.