题目
客户破产无力继续出资,项目刚被取消,约一半交付物已完成。项目经理首先应当做什么?
A project has just been canceled because the customer went bankrupt and cannot finance the remainder. About half the deliverables are complete. What should the project manager do first?
选项
- A.Recall all of the deliverables in the customer's possession
- B.Hold all deliverables that are about to be shipped to the customer
- C.Review the contract and prepare the project closure documents
- D.Turn over all deliverables to the customer whether or not they are complete
解析
解析:项目终止即进入收尾。合同中的终止条款决定已完成与在制交付物的归属,因此必须先弄清法律义务,再准备收尾文件。
Rationale:Termination starts project closure. The contract's termination clause determines ownership of completed and in-progress deliverables, so the legal obligations must be understood first.