结束项目与阶段收尾 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-570

题目

客户破产无力继续出资,项目刚被取消,约一半交付物已完成。项目经理首先应当做什么?
A project has just been canceled because the customer went bankrupt and cannot finance the remainder. About half the deliverables are complete. What should the project manager do first?

选项

  1. A.Recall all of the deliverables in the customer's possession
  2. B.Hold all deliverables that are about to be shipped to the customer
  3. C.Review the contract and prepare the project closure documents
  4. D.Turn over all deliverables to the customer whether or not they are complete
正确答案:C

解析

解析:项目终止即进入收尾。合同中的终止条款决定已完成与在制交付物的归属,因此必须先弄清法律义务,再准备收尾文件。 Rationale:Termination starts project closure. The contract's termination clause determines ownership of completed and in-progress deliverables, so the legal obligations must be understood first.

同考点练习题